Construction:
The building is nearing completion as the steel has been
erected, panels have been installed, and the doors are being completed this
week. The last bit of work left to complete utility related. Installation of
our electrical (800+ amps of a 480v, 3-ph) and natural gas (3” high pressure
line for a 8.7 MBTU burner) is progressing.
Machine:
Our first shipment arrived on 10/1 with three more shipments
scheduled between 10/3 and 10/8. Our final shipments will arrive on or around
10/17. We will be very busy assembling this machine. It will take nearly a
month to assemble, hock-up, and work the “bugs” out. Keep on the “look-out,”
there have been many press releases to date on Rotek and this machine in
national plastics and trade publications.